Reeves Contracting completed installation of one junction box in Church Street and will finish the second box early next week. Once both junction boxes are installed, new catch basins and inlets will be installed to connect existing storm lines to the new drainage system.
Reeves also will complete the replacement of the old water lines on East Maple Street. This will require shutting water service for a period of time. This work will be done after midnight to minimize the inconvenience. A notice will be emailed when this work is scheduled.
Traffic control measures have been established on Church Street until it is reopened, so expect traffic delays in this area.