Reeves Contracting has begun staking out the new curbing and sidewalks on East Maple Street and will be grading the area through the beginning of the week. If the weather cooperates, new curbing will be installed starting late in the week with new sidewalks to follow. A new water line will be installed down the middle of East Maple Street with new service connections to all buildings.
AT&T continues its replacement of the underground telephone cable on North McDonough Street. As soon as this is completed, new drainage inlets will be installed on both corners at North McDonough Street and East Maple and repaving of North McDonough and East Maple will start.
The Rape Crisis Center building will be stabilized starting the week of July 29. Once this is completed, the new 48” storm line will be extended to Church Street and a new phase of the work will begin.
Traffic control measures will remain in place on North McDonough Street, so expect traffic delays.