Rainy weather and a broken sanitary sewer were this week’s challenges. Work should be finished shoring up the LexTechs shop at North McDonough and East Maple in the next day or so. Once this is completed, Reeves Contracting will resume installation of the new 54” storm line and a new water line on East Maple Street.
AT&T will soon replace a telephone cable on North McDonough Street and a portion of North McDonough Street will be repaved. It is expected that completion of the storm and water lines on East Maple Street will take 6-8 weeks.
Once the work nears Church Street, Reeves plans to install new sidewalks and pave East Maple Street. This should allow restoration of vehicle access to the properties on East Maple Street from North McDonough.
Traffic control measures will remain in place on North McDonough Street, so expect traffic delays.
Work will continue this week on the new south line while the contractor shores up the area next to the LexTechs shop at North McDonough and East Maple. Once shoring is complete, Reeves will resume laying the new north line.